Bigger, better Swan Hill District Health taking shape

The second stage of the major redevelopment at Swan Hill District Health has achieved a significant milestone.

The new multi-storey community mental health facility we’re building is structurally complete – paving the way for the building’s striking facade and internal fit-out to progress.

More than 3000 cubic metres of concrete, 45 tonnes of structural steel and a whopping 277 tonnes of steel reinforcement have helped the facility rise from the ground up. Take a look.

A new multi-storey community mental health facility at Swan Hill District Health is on track to be completed next year.

[Text on screen: More than 3000 cubic metres of concrete]

[Images: time lapse footage of construction site with diggers and excavators ]

[Text on screen: 45 tonnes of structural steel]

[Images: time lapse of steel reinforcement rods being delivered]

[Text on screen: and a whopping 277 tonnes of steel reinforcement ]

[Images: time lapse of earthworks and steel scaffolding being erected]

[Text on screen: have helped a new multi-storey community mental health facility at Swan Hill District Health rise from the ground up]

[Images: time lapse of pipes and building cladding being applied]

[Text on screen: On track to be completed in 2026, the project is delivering more spaces for community mental health services, consulting rooms and modern workspaces for healthcare workers]

[Images: time lapse of metal grids and concreting activity; crane lifting struts and beams]

[Text on screen: Giving locals better access to the care and support they need, close to home]

[Images: A partnership transition screen displays the text ‘In partnership with’ and the Swan Hill District Health logo]

[Images: A sliding transition screen then displays the Victorian Health Building Authority and Victoria State Government logos and the url vhba.vic.gov.au]

[End of transcript]

On track to be completed in 2026, the community mental health facility includes:

  • more space for mental health services
  • consulting rooms
  • modern workspaces for health care workers
  • cafeteria
  • lounge area.

The project

The project is the second and final stage of the $65.7 million redevelopment at Swan Hill District Health.

The first stage of the project delivered a new and expanded emergency department, which more than doubled the amount of treatment spaces. The new emergency department includes a four-bed short-stay unit, an isolation room and a behavioural assessment room.

Learn more about the Swan Hill District Health emergency department redevelopment.

Related content

An interior view of Swan Hill District Health's sub-acute care facility

20 March 2025

Swan Hill District Health - Sub-acute care services

The Victorian Government invested $2.6 million to expand sub-acute care facilities at Swan Hill District Health.
Project
Red emergency sign contrasts against the green roof and blue sky

13 March 2025

Swan Hill District Health emergency department redevelopment

The Victorian Government invested $35.7 million to redevelop the Swan Hill District Health emergency department.
Project
Green and red signage among leafy surrounds

13 March 2025

Redeveloped Swan Hill District Health emergency department opens its doors

Construction on the new state-of-the-art emergency department at Swan Hill is now complete.
News
Last updated: 08 October 2025